In October, a concrete retaining wall was built and the new workshop was constructed. Progress has been made on building a ramp so wheelchair users can access the training room. Preparations are underway to transport Dick’s Folly and Pickle’s Folly to Aylesbury in the New Year for repainting. Both boats will be painted with the […]
In July, further work was done on the new training cabin. The plumbing was completed, the carpet tiles laid and all of the cabinets were installed. Work was done on the shutters to make them more secure and compact when open. Further coats of paint were added to the toilet shed, resulting in a more sedate shade than the previous […]
In April, volunteers installed the plumbing in the new training room, ahead of the scheduled build in mid-May. The toilet shed was painted and an additional coat of paint was added to the boat tillers. All the blinds were fitted to Pickle’s Folly and Dick’s Folly and the exteriors of both boats were washed down. […]
Both Pickle’s Folly and Dick’s Folly were serviced in February. Following some minor repairs, Pickle’s Folly passed a Royal Yacht Association inspection.